Construction Updates

July 2026

Horizon Construction Gallery

Phase 1 construction of Horizon's GPU racks is nearly complete, and early users are already accessing the system. The official early user period will begin in late summer 2026, and Phase 2 construction of the CPU portion of the system will later this year.


March 2026

New LCCF Datacenter Nears Completion

The first step in the construction of the National Science Foundation’s Leadership Class Computing Facility is to give the system a new home!


March 2026

Installation of NSF LCCF Horizon Supercomputer is Underway

With the new datacenter’s interior buildout nearing completion, the first components of the Horizon supercomputer have been delivered and construction has begun!


March 2026

Proposals for Allocations on NSF LCCF Horizon to begin April 15, 2026

The NSF Leadership Class Computing Facility will begin accepting allocations for Early Operations of the GPU portion of Horizon on April 15, 2026.